The Boldt Company v. Black & Veatch Construction, Inc. (7th Cir. 2026): A Case Commentary on Construction Schedules, Default Termination and Cost-to-Complete Damages
Clear allocation of delay risk, complete notices and disciplined cost records decide disputes that broad schedule clauses leave open.
A case commentary on construction schedules, default termination and cost-to-complete damages in The Boldt Company v. Black & Veatch Construction, Inc.
Educational purposes only, not legal advice. Independent commentary by a non-attorney; not filed with any court. Read the court's original opinion for the authoritative text.
Case: The Boldt Co. v. Black & Veatch Construction, Inc., Nos. 25-2003 & 25-2070, slip op. (7th Cir. July 8, 2026) (Kirsch, J., for a panel of Scudder, Kirsch and Taibleson, JJ.), on appeal from the Northern District of Illinois, No. 19-cv-08383.
A general contractor claimed nearly $39 million to finish work its subcontractor had agreed to do for $15.4 million. It was awarded $1.
In The Boldt Company v. Black & Veatch Construction, Inc. (7th Cir., 8 July 2026), a windfarm project fell behind almost at once, and the subcontractor was terminated for cause about two months after its work began. The $1 damages award was affirmed. The subcontractor's wrongful termination claim was revived and sent back to be decided, so who was at fault is an open question again.
What you will take from it
- Understand the split result: the $1 damages award was affirmed, summary judgment on two of Boldt's three breach claims was affirmed, and summary judgment on Boldt's wrongful termination claim was reversed and remanded. If liability is later established, the first damages award on cost of completion stands.
- See why declaring schedule performance "a material provision" did not, on the court's reading, by itself place every unexplained delay on the subcontractor, and why notices are judged by what they say, not what they are called.
- Follow the commentary's general observations for project leaders: say who bears unexplained delay, make delay notices complete, and keep cost records clean enough to prove what completion really cost.
- Note the open questions on remand, including whether the parties intended Boldt to bear delays absent effective notice and whether Boldt's notices were adequate.
- This is independent commentary by a non-attorney for educational purposes, not legal advice.
For parties to construction contracts, the most practical lesson of Boldt is that clear allocation of delay risk, complete notices and disciplined cost records decide disputes that broad schedule clauses leave open.
Background
Black & Veatch was the general contractor for a 60-turbine windfarm in Good Hope, Illinois, and subcontracted turbine assembly to The Boldt Company. The subcontract incorporated a construction schedule that Boldt had developed and stated that performance according to that schedule was "a material provision." The project fell behind almost at once. Black & Veatch terminated the subcontract for cause about two months after Boldt's work began.
Black & Veatch claimed nearly $39 million to complete work that Boldt had agreed to perform for $15.4 million. It was awarded $1. The Seventh Circuit affirmed that damages award and the denial of the post-trial motions, affirmed summary judgment on two of Boldt's three breach claims, reversed summary judgment on Boldt's wrongful termination claim and remanded. It also held that if Black & Veatch ultimately establishes liability on remand, the first damages award on cost of completion stands.
Frequently asked questions
- What did the Court hold?
- It affirmed the $1 damages award, affirmed summary judgment on two of Boldt's three breach claims, reversed summary judgment on Boldt's wrongful termination claim and remanded. If liability is later established, the first damages award on cost of completion stands.
- Why was a claim of nearly $39 million reduced to $1?
- The commentary reports that a contractor seeking cost-to-complete damages must give a reliable basis for computing them, and that coding errors and unexplained review methods can reduce a claim of nearly $39 million to $1.
- Is this legal advice?
- No. It is independent commentary by a non-attorney for educational purposes, with general observations for project owners, contractors and subcontractors, not advice about any contract or dispute.
Source
- Author: Thomas Guerriero (Thomas A. Guerriero, PhD; ORCID 0009-0001-9456-8654)
- Official opinion: https://media.ca7.uscourts.gov/cgi-bin/OpinionsWeb/processWebInputExternal.pl?Path=Y2026%2FD07-08%2FC%3A25-2003%3AJ%3AKirsch%3Aaut%3AT%3AfnOp%3AN%3A3570048%3AS%3A0&Submit=Display
- Commentary published: 2026-11-25
- PDF: boldt-v-black-veatch.pdf
More from Thomas Guerriero
See all research and commentary at Research, and the main hub at ThomasGuerriero.com. Also: ThomasAGuerrieroPhD.com · ThomasAGuerriero.com.
For educational purposes only; not legal advice. This page summarises independent commentary on a public court opinion and links to the original. A PDF of the commentary is available on this page.